해양플랜트 의장품 조달관리를 위한 배관 공정 리드타임 예측 모델에 관한 연구
기관명 | NDSL |
---|---|
저널명 | 大韓造船學會 論文集 = Journal of the Society of Naval Architects of Korea |
ISSN | 1225-1143, |
ISBN |
저자(한글) | 함동균,백명기,박중구,우종훈 |
---|---|
저자(영문) | |
소속기관 | |
소속기관(영문) | |
출판인 | |
간행물 번호 | |
발행연도 | 2016-01-01 |
초록 | In shipbuilding and offshore plant construction, pipe-stools of various types are installed. Moreover, these are many quantities but they must be installed in a successive manner. Due to these characteristics the pipe-stool installation processes easily tends to cause the schedule delays in the overall production processes. In order to reduce delay, the goal of this study is to predicts production #x2019;s lead time before manufacturing. Through this predictions it #x2019;s expected to reduce total production #x2019;s lead time by improving it's process. First of all, we made MLR(Multiple Linear Regression) and PLSR(Partial Least Square Regression) model to predict pipe-spool's lead time and then compared predictability of MLR and PLSR model. If a explanatory variable is added, it will be possible to predict results precisely. |
원문URL | http://click.ndsl.kr/servlet/OpenAPIDetailView?keyValue=03553784&target=NART&cn=JAKO201611366386270 |
첨부파일 |
과학기술표준분류 | |
---|---|
ICT 기술분류 | |
DDC 분류 | |
주제어 (키워드) | 선박건조,생산계획,시뮬레이션모델링,표준화,중립파일포맷,Shipbuilding,Production planning,Simulation modelling,Standardization,Neutral file format |